As December 2023 wound down, McCann Concrete Products’ truckers and loading crew were busy sending out the final loads to wrap-up a busy year of precast soundwall manufacturing. McCann soundwalls hit each corner of the State of Missouri this year.

In the spring, Capital Paving installed 41,000 SF of wall in Springfield, MO along Route 60 in southern Missouri. These three walls were part of upgrades to pavement and bridges along Route 60 between Campbell and National Avenues.

In the fall, Pyramid Excavating installed 25,000 SF of soundwall in Blue Springs, MO along I-70 in west Missouri. This wall was part of the bridge replacement at Blue Ridge Boulevard over I-70, in addition to interchange improvements.

Throughout the year, Millstone Weber installed 104,000 SF of wall along I-270 North in St. Louis, MO.  This is part of the multi-year I-270 North Design-Build project. The project included five soundwalls totaling more than 130,000 SF.

With continued investment in American infrastructure, we anticipate another busy year in 2024.